E46 BMW Social Directory E46 FAQ 3-Series Discussion Forums BMW Photo Gallery BMW 3-Series Technical Information E46 Fanatics - The Ultimate BMW Resource BMW Vendors General E46 Forum The Tire Rack's Tire Wheel Forum Forced Induction Forum The Off-Topic The E46 BMW Showroom For Sale, For Trade or Wanting to Buy

Welcome to the E46Fanatics forums. E46Fanatics is the premiere website for BMW 3 series owners around the world with interactive forums, a geographical enthusiast directory, photo galleries, and technical information for BMW enthusiasts.

You are currently viewing our boards as a guest which gives you limited access to view most discussions and access our other features. By joining our free community you will have access to post topics, communicate privately with other members (PM), respond to polls, upload content and access many other special features. Registration is fast, simple and absolutely free so please, join our community today!

If you have any problems with the registration process or your account login, please contact contact us.

Go Back   E46Fanatics > Everything Else > The Off-Topic > Home Improvement

Home Improvement
Home Improvement ideas, help, DIYs, and show room. Got a home improvement project you need help with or want to share. Post your project now!

 
 
Thread Tools Search this Thread Rating: Thread Rating: 2 votes, 5.00 average. Display Modes
Prev Previous Post   Next Post Next
Old 08-30-2012, 09:36 PM   #1
LAFENGAS
www.thielstudios.com
 
LAFENGAS's Avatar
 
Join Date: Jan 2003
Location: West Palm Beach, FL
Posts: 1,332
My Ride: 330ci
Send a message via AIM to LAFENGAS
Arrow DIY: Entire Basement Rennovation: Nothing to Something

Again sort of a repost now that there's "Home Improvement" forum.

Figured i may as well start a thread mid-process. Since i now have 2 kids, I chose to put each kid in their own room up on the 2nd floor, plus there is a loft up there that can be used as a play room which keeps everything up there.

So I decided to put a bed/bath in the basement for the wifey and I ...as well as help make the unit more rentable when it comes time.

here was the clean slate, the day i took ownership:









Here's a general layout of the basement and what i'm hoping to accomplish:




What needs to be done:

1.) Move support post: one support post is in the proposed living space, and will be relocated. W8x15 support beam can support the added unbraced distance of the support relocation

2.) Add a decent sized bathroom: Install a bathroom in the proximity of the existing sewer line. sewage pump will need to be installed to pump poop to the sewer

3.) Storage Space: Would like some decent usable storage space

4.) Bedroom and Closet: add a decent sized bedroom and closet, keep the high cielings where possible and adding drop cieling where needed to access utilities above.




I decided to go with steel beams for the framing for a few reasons. 1.) the walls are not load bearing. 2.) steel doesn't warp or mold 3.) Price is nearly the same as a wood 2x4. 4.) lightweight and easy to handle. 5.) I like metal.


Day 1: layout of the walls and plumbing for the bath:




Day 2: Prep for concrete cutting




Day 3: Saw Cut and Break the concrete: (dusty as ****)


4hrs Later:

Started the framing, same day:



Day 4: ran all the plumbing and I backfilled all the concrete. Sewage pump buried and running into the existing sewer lines.



more framing:


bathroom walls going up:


hallway walls in the back:


closet in the back right, framed for 36" pocket doors:


Day 5, more hallway framing: ( Notice the support post has been pulled.)



Walls up, Electrical run. Notice the Red Support Post. I cut a 18"x18" section of concrete floor out and poured a 12" pad for the new support beam to rest on (waited 3 days for the concrete to setup before putting any load on it)


Day 9: Framing complete, I-beam boxed in...READY TO DRYWALL:



Everything was pressure tested and no leaks.


Shower:


Storage Closet:


Day 14: drywalling:




Closet:


Day 20: finishing work on the drywall (still need to work on the bath)








1 month milestone:

Carpet is getting installed as we speak, hopefully the hardwood this weekend.

Finished all the drywall work lastnight and put a coat of primer on everything.









hallway:


I decided to use bifold closet doors for access to utilities:



used some motar mix to fill in the stress relief seams so i don't feel them through the carpet:


working on the bathroom now to try bringing it to the same level of compeltion as the bedroom which is awaiting trim work.

FYI, working with HardyBacker board is a huge PITA! I found the best way to cut it is using a recipicating saw... it seems to just chew through blades. Using a knife, scoring and breaking isn't working...this stuff appears to be laminated so you can't break it like drywall. It's also hard to screw near the edges without it exploding

Anyway, i put the shower pan liner in place, filled it with 3" of water and let it set for a day to make sure there were no leaks. No issues. Lined the shower with 6mil plastic and overlapped it over the pan liner (40mil Vinyl). Right now i'm working on getting the cement board in place.



When i designed the shower wall layout I didn't realize this **** came as 3'x5' sheets, otherwise i would have spaced the studs accordingly....so every sheet needs to be trimmed to fit. lame.

here's the progress:


LAFENGAS is offline   Reply With Quote
 

Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is On
Censor is ON





All times are GMT -5. The time now is 05:37 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2014, vBulletin Solutions, Inc.
(c) 1999 - 2011 performanceIX Inc - privacy policy - terms of use